Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-13 17:34:39 | Cancellations to services at Kirkdale | |
Date / Time Resolved | 2025-01-13 18:35:02 | ||
Due to a train fault at Kirkdale the Headbolt Lane and Ormskirk line is disrupted. Impact: Train services running through this station may be cancelled or delayed. Disruption is expected until 18:30 13/01. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-13 11:26:01 | Cancellations to services at Sandhills | |
Date / Time Resolved | 2025-01-13 12:05:02 | ||
Due to animals on the railway at Sandhills the Northern line is disrupted. Impact: Train services running through this station are returning to normal but some services will still be cancelled or delayed. Disruption is expected until 12:00 13/01. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-13 11:03:35 | Cancellations to services at Sandhills | |
Date / Time Resolved | 2025-01-13 11:30:02 | ||
Due to animals on the railway at Sandhills the Northern line is disrupted. Impact: Train services running through this station will be cancelled or delayed. Disruption is expected until 12:00 13/01. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-13 10:40:51 | Delays to services at Sandhills | |
Date / Time Resolved | 2025-01-13 11:10:01 | ||
Due to animals on the railway at Sandhills the Northern line is disrupted. Impact: Train services running through this station may be delayed. Disruption is expected until 11:45 13/01. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-11 04:57:06 | Delays to services between Brunswick and Liverpool Cntrl Northern | |
Date / Time Resolved | 2025-01-11 10:05:01 | ||
Due to a faulty signal between Brunswick and Liverpool Cntrl Northern the Ormskirk and Hunts Cross line is disrupted. Impact: Train services running through these stations may be delayed by up to 10 minutes. Disruption is expected until 10:00 11/01. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-10 08:56:25 | Delays to services to Hunts Cross | |
Date / Time Resolved | 2025-01-10 09:30:02 | ||
Due to earlier signalling problems at Liverpool Cntrl Northern the Ormskirk and Hunts Cross line is disrupted. Disruption is expected until 09:30 10/01. Impact: Train services to Hunts Cross are returning to normal but some services may still be delayed. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-10 08:56:25 | Delays to services to Ormskirk | |
Date / Time Resolved | 2025-01-10 09:30:02 | ||
Due to earlier signalling problems at Liverpool Cntrl Northern the Ormskirk and Hunts Cross line is disrupted. Disruption is expected until 09:30 10/01. Impact: Train services to Ormskirk are returning to normal but some services may still be delayed. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-10 08:30:59 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2025-01-10 09:00:02 | ||
Due to signalling problems at Liverpool Cntrl Northern the Ormskirk and Hunts Cross line is disrupted. Disruption is expected until 10:00 10/01. Impact: Train services to Ormskirk may be cancelled or delayed by up to 15 minutes. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-10 08:30:59 | Cancellations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-10 09:00:02 | ||
Due to signalling problems at Liverpool Cntrl Northern the Ormskirk and Hunts Cross line is disrupted. Disruption is expected until 10:00 10/01. Impact: Train services to Hunts Cross may be cancelled or delayed by up to 15 minutes. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-10 07:54:19 | Cancellations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-10 08:35:02 | ||
Due to signalling problems at Liverpool Cntrl Northern the Ormskirk and Hunts Cross line is disrupted. Disruption is expected until 09:00 10/01. Impact: Train services to Hunts Cross may be cancelled or delayed. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-10 07:54:19 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2025-01-10 08:35:02 | ||
Due to signalling problems at Liverpool Cntrl Northern the Ormskirk and Hunts Cross line is disrupted. Disruption is expected until 09:00 10/01. Impact: Train services to Ormskirk may be cancelled or delayed. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 15:08:01 | Cancellations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-09 17:50:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 17:00 09/01. Impact: Train services to Hunts Cross are returning to normal but some services will still be cancelled or delayed. Customer Advice: A limited rail service will be in operation on the Hunts Cross Line. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 15:08:01 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2025-01-09 17:50:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 17:00 09/01. Impact: Train services to Ormskirk are returning to normal but some services will still be cancelled or delayed. Customer Advice: A limited rail service will be in operation on the Ormskirk Line. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 13:39:19 | Cancellations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-09 15:15:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 16:00 09/01. Impact: Train services to Hunts Cross are returning to normal but some services will still be cancelled or delayed. Customer Advice: A limited rail service will be in operation on the Hunts Cross Line. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 13:39:19 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2025-01-09 15:15:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 16:00 09/01. Impact: Train services to Ormskirk are returning to normal but some services will still be cancelled or delayed. Customer Advice: A limited rail service will be in operation on the Ormskirk Line. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 13:22:40 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-09 13:45:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 14:00 09/01. Impact: Train services to Hunts Cross will be suspended. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 13:22:40 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-09 13:45:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 14:00 09/01. Impact: Train services to Ormskirk will be suspended. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 12:57:10 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-09 13:30:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 15:00 09/01. Impact: Train services to Hunts Cross will be suspended. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 12:57:10 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-09 13:30:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 15:00 09/01. Impact: Train services to Ormskirk will be suspended. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 12:43:50 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-09 13:05:01 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 14:00 09/01. Impact: Train services to Ormskirk will be suspended. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 12:43:50 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-09 13:05:01 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 14:00 09/01. Impact: Train services to Hunts Cross will be suspended. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 12:35:42 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-09 12:50:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 14:00 09/01. Impact: Train services to Hunts Cross are returning to normal but some services will still be suspended. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 12:35:42 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-09 12:50:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 14:00 09/01. Impact: Train services to Ormskirk will be suspended. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 12:29:40 | Cancellations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-09 12:40:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 14:00 09/01. Impact: Train services to Hunts Cross are returning to normal but some services will still be cancelled or delayed. Customer Advice: A very limited service is operating on the Ormskirk and Hunts Cross lines. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 12:29:40 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-09 12:40:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 14:00 09/01. Impact: Train services to Ormskirk will be suspended. Customer Advice: A very limited service is operating between Liverpool and Hunts Cross. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 11:54:32 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2025-01-09 12:35:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 14:00 09/01. Impact: Train services to Ormskirk are returning to normal but some services will still be cancelled or delayed. Customer Advice: A very limited service is operating on the Ormskirk and Hunts Cross lines. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 11:54:32 | Cancellations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-09 12:35:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 14:00 09/01. Impact: Train services to Hunts Cross are returning to normal but some services will still be cancelled or delayed. Customer Advice: A very limited service is operating on the Ormskirk and Hunts Cross lines. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 10:00:50 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-09 12:00:03 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 14:00 09/01. Impact: Train services to Hunts Cross will be suspended. Additional Information: We are unable to obtain any buses and advise passengers to make alternative arrangements where possible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 10:00:50 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-09 12:00:03 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 14:00 09/01. Impact: Train services to Ormskirk will be suspended. Customer Advice: Passengers travelling between Liverpool and Walton are advised to use Headbolt Lane services. Additional Information: We are unable to obtain any buses and advise passengers to make alternative arrangements where possible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 09:20:15 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-09 10:05:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 12:00 09/01. Impact: Train services to Ormskirk will be suspended. Customer Advice: Passengers travelling between Liverpool and Walton are advised to use Headbolt Lane services. Additional Information: We are unable to obtain any buses and advise passengers to make alternative arrangements where possible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 09:20:15 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-09 10:05:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 12:00 09/01. Impact: Train services to Hunts Cross will be suspended. Additional Information: We are unable to obtain any buses and advise passengers to make alternative arrangements where possible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 09:03:59 | Cancellations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-09 09:25:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 12:00 09/01. Impact: Train services to Hunts Cross will be cancelled, delayed or terminated at and started back from Liverpool Cntrl Northern. Additional Information: We are unable to obtain any buses and advise passengers to make alternative arrangements where possible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 09:03:59 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-09 09:25:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 12:00 09/01. Impact: Train services to Ormskirk will be suspended. Customer Advice: Passengers travelling between Liverpool and Walton are advised to use Headbolt Lane services. Additional Information: We are unable to obtain any buses and advise passengers to make alternative arrangements where possible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 08:57:53 | Cancellations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-09 09:10:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 12:00 09/01. Impact: Train services to Hunts Cross will be cancelled, delayed or terminated at and started back from Liverpool Cntrl Northern. Additional Information: We are unable to obtain any buses and advise passengers to make alternative arrangements where possible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 08:57:53 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2025-01-09 09:10:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 12:00 09/01. Impact: Train services to Ormskirk will be cancelled, delayed or terminated at and started back from Walton Merseyside. Additional Information: We are unable to obtain any buses and advise passengers to make alternative arrangements where possible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 08:49:15 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2025-01-09 09:00:03 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 11:00 09/01. Impact: Train services to Ormskirk will be cancelled, delayed or terminated at and started back from Walton Merseyside. Additional Information: We are unable to obtain any buses and advise passengers to make alternative arrangements where possible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 08:49:15 | Cancellations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-09 09:00:03 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 11:00 09/01. Impact: Train services to Hunts Cross will be cancelled, delayed or terminated at and started back from Liverpool Cntrl Northern. Additional Information: We are unable to obtain any buses and advise passengers to make alternative arrangements where possible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 08:12:27 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2025-01-09 08:55:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 11:00 09/01. Impact: Train services to Ormskirk will be cancelled or delayed. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 08:12:27 | Cancellations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-09 08:55:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 11:00 09/01. Impact: Train services to Hunts Cross will be cancelled or delayed. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 07:50:23 | Cancellations to services between Ormskirk and Hunts Cross | |
Date / Time Resolved | 2025-01-09 08:15:03 | ||
Due to poor weather conditions between Ormskirk and Hunts Cross the Ormskirk and Hunts Cross line is disrupted. Impact: Train services running to and from these stations will be cancelled or delayed. Disruption is expected until 10:00 09/01. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 07:15:05 | Cancellations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-09 08:20:19 | ||
Due to a train fault at Sandhills the Northern line is disrupted. Disruption is expected until 08:15 09/01. Impact: Train services to Hunts Cross are returning to normal but some services may still be cancelled or delayed. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 07:15:05 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2025-01-09 08:20:19 | ||
Due to a train fault at Sandhills the Northern line is disrupted. Disruption is expected until 08:15 09/01. Impact: Train services to Ormskirk are returning to normal but some services may still be cancelled or delayed. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 07:10:40 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2025-01-09 07:20:02 | ||
Due to a train fault at Sandhills the Northern line is disrupted. Disruption is expected until 08:15 09/01. Impact: Train services to Ormskirk may be cancelled or delayed. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-09 07:10:40 | Cancellations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-09 07:20:02 | ||
Due to a train fault at Sandhills the Northern line is disrupted. Disruption is expected until 08:15 09/01. Impact: Train services to Hunts Cross may be cancelled or delayed. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 15:26:23 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2025-01-07 15:50:02 | ||
Due to poor weather conditions between Maghull and Ormskirk the Ormskirk line is disrupted. Disruption is expected until 15:45 07/01. Impact: Train services to Ormskirk are returning to normal but some services will still be cancelled or delayed. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 15:14:50 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-07 15:30:02 | ||
Due to poor weather conditions between Maghull and Ormskirk the Ormskirk line is disrupted. Disruption is expected until 17:00 07/01. Impact: Train services to Ormskirk will be terminated at and started back from Maghull. Additional Information: A Rail Replacement Bus is now in operation only calling Maghull and Omskirk. This is due to poor weather conditions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 14:19:52 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-07 15:20:02 | ||
Due to poor weather conditions between Maghull and Ormskirk the Ormskirk line is disrupted. Disruption is expected until 17:00 07/01. Impact: Train services to Ormskirk will be terminated at and started back from Maghull. Additional Information: A Rail Replacement Bus is now in operation only calling Maghull and Omskirk. This is due to poor weather conditions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 13:24:17 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-07 14:25:01 | ||
Due to poor weather conditions between Maghull and Ormskirk the Ormskirk line is disrupted. Disruption is expected until 14:30 07/01. Impact: Train services to Ormskirk will be terminated at and started back from Maghull. Additional Information: A Rail Replacement Bus is now in operation only calling Maghull and Omskirk. This is due to poor weather conditions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 13:19:11 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-07 13:30:01 | ||
Due to poor weather conditions between Maghull and Ormskirk the Ormskirk line is disrupted. Disruption is expected until 14:30 07/01. Impact: Train services to Ormskirk will be terminated at and started back from Maghull. Additional Information: A Rail Replacement Bus is now in operation only calling Maghull, Maghull North and Omskirk. This is due to poor weather conditions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 12:15:36 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-07 13:25:02 | ||
Due to poor weather conditions between Maghull and Ormskirk the Ormskirk line is disrupted. Disruption is expected until 14:30 07/01. Impact: Train services to Ormskirk will be terminated at and started back from Maghull. Additional Information: A limited replacement bus service has been requested to run between Maghull and Ormskirk in both directions. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 11:45:44 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-07 12:20:02 | ||
Due to poor weather conditions between Maghull and Ormskirk the Ormskirk line is disrupted. Disruption is expected until 14:00 07/01. Impact: Train services to Ormskirk will be terminated at and started back from Maghull. Additional Information: Replacement buses have been requested to run between Maghull and Ormskirk, however due to the poor weather conditions no buses are currently avaliable. Customers advised to make alternative travel arrangements where psossible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 11:17:27 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-07 11:50:01 | ||
Due to poor weather conditions between Maghull and Ormskirk the Ormskirk line is disrupted. Disruption is expected until 13:00 07/01. Impact: Train services to Ormskirk will be terminated at and started back from Maghull. Additional Information: Replacement buses have been requested to run between Maghull and Ormskirk, however due to the poor weather conditions no buses are currently avaliable. Customers advised to make alternative travel arrangements where psossible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 10:21:55 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-07 11:20:01 | ||
Due to poor weather conditions between Maghull and Ormskirk the Ormskirk line is disrupted. Disruption is expected until 13:00 07/01. Impact: Train services to Ormskirk will be terminated at and started back from Maghull. Additional Information: Replacement buses have been requested to run between Maghull and Ormskirk, however due to the poor weather conditions no buses are currently avaliable. Customers advised to make alternative travel arrangements where psossible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 09:26:05 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-07 10:25:02 | ||
Due to poor weather conditions between Maghull and Ormskirk the Ormskirk line is disrupted. Disruption is expected until 12:00 07/01. Impact: Train services to Ormskirk will be terminated at and started back from Maghull. Additional Information: Replacement buses have been requested to run between Maghull and Ormskirk, however due to the poor weather conditions no buses are currently avaliable. Customers advised to make alternative travel arrangements where psossible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 09:24:30 | Cancellations to services between Liverpool South Pw Ll and Hunts Cross | |
Date / Time Resolved | 2025-01-07 10:25:02 | ||
Due to a tree blocking the railway between Liverpool South Pw Ll and Hunts Cross the Ormskirk and Hunts Cross line is disrupted. Impact: Train services running through these stations are returning to normal but some services may still be cancelled or delayed. Disruption is expected until 11:00 07/01. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 08:58:38 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-07 09:30:02 | ||
Due to poor weather conditions between Maghull and Ormskirk the Ormskirk line is disrupted. Disruption is expected until 11:00 07/01. Impact: Train services to Ormskirk will be terminated at and started back from Maghull. Additional Information: Replacement buses have been requested to run between Maghull and Ormskirk, however due to the poor weather conditions no buses are currently avaliable. Customers advised to make alternative travel arrangements where psossible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 08:44:52 | Alterations to services between Liverpool South Pw Ll and Hunts Cross | |
Date / Time Resolved | 2025-01-07 09:30:02 | ||
Due to a tree blocking the railway between Liverpool South Pw Ll and Hunts Cross the Ormskirk and Hunts Cross line is disrupted. Impact: Train services running through these stations will be terminated at and started back from Liverpool South Pw Ll. Disruption is expected until 10:00 07/01. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 08:10:44 | Alterations to services between Liverpool South Pw Ll and Hunts Cross | |
Date / Time Resolved | 2025-01-07 09:10:02 | ||
Due to a tree blocking the railway between Liverpool South Pw Ll and Hunts Cross the Ormskirk and Hunts Cross line is disrupted. Impact: Train services running through these stations will be terminated at and started back from Liverpool Cntrl Northern. Disruption is expected until 10:00 07/01. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 08:03:54 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-07 09:10:02 | ||
Due to poor weather conditions between Maghull and Ormskirk the Ormskirk line is disrupted. Disruption is expected until 10:00 07/01. Impact: Train services to Ormskirk will be terminated at and started back from Maghull. Additional Information: Replacement buses have been requested to run between Maghull and Ormskirk, however due to the poor weather conditions no buses are currently avaliable. Customers advised to make alternative travel arrangements where psossible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 07:18:05 | Alterations to services between Liverpool South Pw Ll and Hunts Cross | |
Date / Time Resolved | 2025-01-07 08:15:01 | ||
Due to a tree blocking the railway between Liverpool South Pw Ll and Hunts Cross the Ormskirk and Hunts Cross line is disrupted. Impact: Train services running through these stations will be terminated at and started back from Liverpool Cntrl Northern. Disruption is expected until 09:00 07/01. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 07:11:50 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-07 08:05:02 | ||
Due to poor weather conditions between Maghull and Ormskirk the Ormskirk line is disrupted. Disruption is expected until 09:00 07/01. Impact: Train services to Ormskirk will be terminated at and started back from Maghull. Additional Information: A limited rail replacement bus service has been requested to operate between Maghull and Ormskirk, but this bus service is not yet in operation. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 06:46:09 | Alterations to services to Ormskirk | |
Date / Time Resolved | 2025-01-07 07:15:02 | ||
Due to poor weather conditions between Maghull and Ormskirk the Ormskirk line is disrupted. Disruption is expected until 07:45 07/01. Impact: Train services to Ormskirk will be terminated at and started back from Maghull. Additional Information: A limited rail replacement bus service has been requested to operate between Maghull and Ormskirk, but this bus service is not yet in operation. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 06:09:14 | Alterations to services between Liverpool South Pw Ll and Hunts Cross | |
Date / Time Resolved | 2025-01-07 07:20:02 | ||
Due to a tree blocking the railway between Liverpool South Pw Ll and Hunts Cross the Ormskirk and Hunts Cross line is disrupted. Impact: Train services running through these stations will be terminated at and started back from Liverpool South Pw Ll. Disruption is expected until 08:00 07/01. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-07 05:54:54 | Alterations to services between Liverpool South Pw Ll and Hunts Cross | |
Date / Time Resolved | 2025-01-07 06:15:02 | ||
Due to a tree blocking the railway between Liverpool South Pw Ll and Hunts Cross the Ormskirk and Hunts Cross line is disrupted. Impact: Train services running through these stations will be terminated at and started back from Liverpool South Pw Ll. Disruption is expected until 08:00 07/01. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 21:52:18 | Cancellations to services between Ormskirk and Hunts Cross | |
Date / Time Resolved | 2025-01-06 22:15:01 | ||
Due to a track fault at Liverpool South Pw Ll disruption is expected until 22:15 06/01. Impact: Train services between Ormskirk and Hunts Cross are returning to normal but some services will still be cancelled or delayed. Customer Advice: Due to a track fault services from Ormskirk to Hunts Cross are terminating at Liverpool Central. A rail replacement bus service is in operation from Moorfields calling at all Hunts Cross line stations. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 21:35:49 | Cancellations to services between Ormskirk and Hunts Cross | |
Date / Time Resolved | 2025-01-06 22:00:03 | ||
Due to a track fault at Liverpool South Pw Ll disruption is expected until 22:15 06/01. Impact: Train services between Ormskirk and Hunts Cross are returning to normal but some services will still be cancelled or delayed. Customer Advice: Due to a track fault services from Ormskirk to Hunts Cross are terminating at Liverpool Central. A rail replacement bus service is in operation from Moorfields calling at all Hunts Cross line stations. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 21:13:53 | Alterations to services between Ormskirk and Hunts Cross | |
Date / Time Resolved | 2025-01-06 21:40:01 | ||
Due to a track fault at Liverpool South Pw Ll disruption is expected until 22:15 06/01. Impact: Train services between Ormskirk and Hunts Cross will be terminated at and started back from Liverpool Cntrl Northern. Customer Advice: Due to a track fault services from Ormskirk to Hunts Cross are terminating at Liverpool Central. A rail replacement bus service is in operation from Moorfields calling at all Hunts Cross line stations. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 20:57:20 | Alterations to services between Ormskirk and Hunts Cross | |
Date / Time Resolved | 2025-01-06 21:20:02 | ||
Due to a track fault at Liverpool South Pw Ll disruption is expected until 21:15 06/01. Impact: Train services between Ormskirk and Hunts Cross will be terminated at and started back from Liverpool Cntrl Northern. Customer Advice: Due to a track fault services from Ormskirk to Hunts Cross are terminating at Liverpool Central. A rail replacement bus service is in operation from Moorfields calling at all Hunts Cross line stations. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 20:40:02 | Alterations to services between Ormskirk and Hunts Cross | |
Date / Time Resolved | 2025-01-06 21:00:02 | ||
Due to a track fault at Liverpool South Pw Ll disruption is expected until 21:15 06/01. Impact: Train services between Ormskirk and Hunts Cross will be terminated at and started back from Liverpool Cntrl Northern. Customer Advice: Due to a track fault services from Ormskirk to Hunts Cross are terminating at Liverpool Central. A rail replacement bus has been requested to run from Moorfields calling at all Hunts Cross line stations. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 20:22:39 | Alterations to services between Ormskirk and Hunts Cross | |
Date / Time Resolved | 2025-01-06 20:45:02 | ||
Due to a track fault at Liverpool South Pw Ll disruption is expected until 21:15 06/01. Impact: Train services between Ormskirk and Hunts Cross will be terminated at and started back from Liverpool Cntrl Northern. Customer Advice: Due to a track fault services from Ormskirk to Hunts Cross are terminating at Liverpool Central. A rail replacement bus has been requested to run from Moorfields calling at all Hunts Cross line stations. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 12:32:03 | Trains now running normally to Hunts Cross | |
Date / Time Resolved | 2025-01-06 13:00:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Impact: Train services to Hunts Cross are now running normally. Additional Information: A rail replacement coach service is in place between Liverpool South Parkway and Hunts Cross in both directions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 12:32:03 | Trains now running normally from Hunts Cross | |
Date / Time Resolved | 2025-01-06 13:00:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Impact: Train services from Hunts Cross are now running normally. Additional Information: A rail replacement coach service is in place between Liverpool South Parkway and Hunts Cross in both directions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 11:50:27 | Cancellations to services from Hunts Cross | |
Date / Time Resolved | 2025-01-06 12:40:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 13:00 06/01. Impact: Train services from Hunts Cross are returning to normal but some services will still be cancelled or delayed. Additional Information: A rail replacement coach service is in place between Liverpool South Parkway and Hunts Cross in both directions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 11:50:27 | Cancellations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-06 12:40:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 13:00 06/01. Impact: Train services to Hunts Cross are returning to normal but some services will still be cancelled or delayed. Additional Information: A rail replacement coach service is in place between Liverpool South Parkway and Hunts Cross in both directions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 11:14:35 | Alterations to services from Hunts Cross | |
Date / Time Resolved | 2025-01-06 11:55:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 16:00 06/01. Impact: Train services from Hunts Cross will be delayed by up to 15 minutes or terminated at and started back from Liverpool South Pw Ll. Additional Information: A rail replacement coach service is in place between Liverpool South Parkway and Hunts Cross in both directions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 11:14:35 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-06 11:55:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 16:00 06/01. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool South Pw Ll. Additional Information: A rail replacement coach service is in place between Liverpool South Parkway and Hunts Cross in both directions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 09:29:14 | Delays to services to Ormskirk | |
Date / Time Resolved | 2025-01-06 12:05:01 | ||
Due to a fault with barriers at a level crossing at Maghull the Ormskirk and Hunts Cross line is disrupted. Disruption is expected until 12:00 06/01. Impact: Train services to Ormskirk may be delayed by up to 15 minutes. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 09:24:41 | Alterations to services from Hunts Cross | |
Date / Time Resolved | 2025-01-06 11:20:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 12:00 06/01. Impact: Train services from Hunts Cross will be delayed by up to 15 minutes or terminated at and started back from Liverpool South Pw Ll. Additional Information: A rail replacement coach service is in place between Liverpool South Parkway and Hunts Cross in both directions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 09:24:41 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-06 11:20:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 12:00 06/01. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool South Pw Ll. Additional Information: A rail replacement coach service is in place between Liverpool South Parkway and Hunts Cross in both directions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 08:39:23 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-06 09:30:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 11:00 06/01. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool South Pw Ll. Additional Information: A rail replacement coach service is in place between Liverpool South Parkway and Hunts Cross in both directions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 08:39:23 | Alterations to services from Hunts Cross | |
Date / Time Resolved | 2025-01-06 09:30:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 11:00 06/01. Impact: Train services from Hunts Cross will be delayed by up to 15 minutes or terminated at and started back from Liverpool South Pw Ll. Additional Information: A rail replacement coach service is in place between Liverpool South Parkway and Hunts Cross in both directions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 08:35:54 | Alterations to services from Hunts Cross | |
Date / Time Resolved | 2025-01-06 08:45:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 11:00 06/01. Impact: Train services from Hunts Cross will be delayed by up to 15 minutes or terminated at and started back from Liverpool South Pw Ll. Additional Information: A limited rail replacement coach service is expected to be in place between Liverpool South Parkway and Hunts Cross by 0745. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 08:35:54 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-06 08:45:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 11:00 06/01. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool South Pw Ll. Additional Information: A limited rail replacement coach service is expected to be in place between Liverpool South Parkway and Hunts Cross by 0745. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 07:32:14 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-06 08:40:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 11:00 06/01. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool South Pw Ll. Additional Information: A limited rail replacement coach service is expected to be in place between Liverpool South Parkway and Hunts Cross by 0745. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 07:32:14 | Alterations to services from Hunts Cross | |
Date / Time Resolved | 2025-01-06 08:40:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 11:00 06/01. Impact: Train services from Hunts Cross will be terminated at and started back from Liverpool South Pw Ll. Additional Information: A limited rail replacement coach service is expected to be in place between Liverpool South Parkway and Hunts Cross by 0745. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 07:12:01 | Alterations to services from Hunts Cross | |
Date / Time Resolved | 2025-01-06 07:40:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 10:00 06/01. Impact: Train services from Hunts Cross will be terminated at and started back from Liverpool South Pw Ll. Additional Information: A limited rail replacement coach service is expected to be in place between Liverpool South Parkway and Hunts Cross by 0745. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 07:12:01 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-06 07:40:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 10:00 06/01. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool South Pw Ll. Additional Information: A limited rail replacement coach service is expected to be in place between Liverpool South Parkway and Hunts Cross by 0745. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 06:51:35 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-06 07:20:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 10:00 06/01. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool South Pw Ll. Additional Information: We are unfortunalty unable to obtain a bus service. We advise customers to make alternative arrangements where possible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 06:51:35 | Alterations to services from Hunts Cross | |
Date / Time Resolved | 2025-01-06 07:20:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 10:00 06/01. Impact: Train services from Hunts Cross will be terminated at and started back from Liverpool South Pw Ll. Additional Information: We are unfortunalty unable to obtain a bus service. We advise customers to make alternative arrangements where possible. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 06:09:03 | Alterations to services from Hunts Cross | |
Date / Time Resolved | 2025-01-06 06:55:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 08:00 06/01. Impact: Train services from Hunts Cross will be terminated at and started back from Liverpool South Pw Ll. Additional Information: Buses have requested to run between Liverpool South Parkway and Hunts Cross but are not yet in operation. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 06:09:03 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-06 06:55:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 08:00 06/01. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool South Pw Ll. Additional Information: Buses have requested to run between Liverpool South Parkway and Hunts Cross but are not yet in operation. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 05:53:42 | Alterations to services from Hunts Cross | |
Date / Time Resolved | 2025-01-06 06:15:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 08:00 06/01. Impact: Train services from Hunts Cross will be terminated at and started back from Liverpool South Pw Ll. Additional Information: Buses have requested to run between Liverpool South Parkway and Hunts Cross but are not yet in operation. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-06 05:53:42 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-06 06:15:02 | ||
Due to a points failure at Hunts Cross the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 08:00 06/01. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool South Pw Ll. Additional Information: Buses have requested to run between Liverpool South Parkway and Hunts Cross but are not yet in operation. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-05 09:49:28 | Trains now running normally to Ormskirk | |
Date / Time Resolved | 2025-01-05 10:35:02 | ||
Due to poor weather conditions the Northern line is disrupted. Impact: Train services to Ormskirk are now running normally. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-05 09:49:28 | Trains now running normally to Hunts Cross | |
Date / Time Resolved | 2025-01-05 10:35:02 | ||
Due to poor weather conditions the Northern line is disrupted. Impact: Train services to Hunts Cross are now running normally. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-05 08:45:22 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2025-01-05 09:55:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 11:45 05/01. Impact: Train services to Ormskirk may be cancelled or delayed. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2025-01-05 08:45:22 | Cancellations to services to Hunts Cross | |
Date / Time Resolved | 2025-01-05 09:55:02 | ||
Due to poor weather conditions the Northern line is disrupted. Disruption is expected until 11:45 05/01. Impact: Train services to Hunts Cross may be cancelled or delayed. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-31 17:16:56 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2024-12-31 18:05:01 | ||
Due to signalling problems at Liverpool Cntrl Northern the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 18:00 31/12. Impact: Train services to Ormskirk are returning to normal but some services may still be cancelled or delayed. Additional Information: If you have suffered delay as a result of this incident you may be entitled to compensation. Please visit https://www.merseyrail.org/contact-us/refunds-and-compensation.aspx for further information |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-31 17:16:56 | Cancellations to services to Hunts Cross | |
Date / Time Resolved | 2024-12-31 18:05:01 | ||
Due to signalling problems at Liverpool Cntrl Northern the Hunts Cross and Ormskirk line is disrupted. Disruption is expected until 18:00 31/12. Impact: Train services to Hunts Cross are returning to normal but some services may still be cancelled or delayed. Additional Information: If you have suffered delay as a result of this incident you may be entitled to compensation. Please visit https://www.merseyrail.org/contact-us/refunds-and-compensation.aspx for further information |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-31 16:56:00 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2024-12-31 17:20:02 | ||
Due to signalling problems at Liverpool Cntrl Northern the Headbolt Lane and Ormskirk line is disrupted. Disruption is expected until 17:30 31/12. Impact: Train services to Ormskirk are returning to normal but some services may still be cancelled or delayed. Additional Information: If you have suffered delay as a result of this incident you may be entitled to compensation. Please visit https://www.merseyrail.org/contact-us/refunds-and-compensation.aspx for further information |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-31 16:36:17 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2024-12-31 17:00:02 | ||
Due to signalling problems at Liverpool Cntrl Northern the Headbolt Lane and Ormskirk line is disrupted. Disruption is expected until 17:30 31/12. Impact: Train services to Ormskirk may be cancelled or delayed. Additional Information: If you have suffered delay as a result of this incident you may be entitled to compensation. Please visit https://www.merseyrail.org/contact-us/refunds-and-compensation.aspx for further information |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-31 16:11:40 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2024-12-31 16:40:02 | ||
Due to signalling problems at Liverpool Cntrl Northern the Ormskirk line is disrupted. Disruption is expected until 17:00 31/12. Impact: Train services to Ormskirk may be cancelled or delayed. Additional Information: If you have suffered delay as a result of this incident you may be entitled to compensation. Please visit https://www.merseyrail.org/contact-us/refunds-and-compensation.aspx for further information |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-31 15:51:34 | Delays to services to Ormskirk | |
Date / Time Resolved | 2024-12-31 16:15:02 | ||
Due to signalling problems at Liverpool Cntrl Northern the Ormskirk line is disrupted. Disruption is expected until 17:00 31/12. Impact: Train services to Ormskirk may be delayed. Additional Information: If you have suffered delay as a result of this incident you may be entitled to compensation. Please visit https://www.merseyrail.org/contact-us/refunds-and-compensation.aspx for further information |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-31 11:28:45 | Cancellations to services to Liverpool Cntrl Northern | |
Date / Time Resolved | 2024-12-31 12:05:01 | ||
Due to an earlier train fault at Bootle Oriel Road disruption is expected until 12:00 31/12. Impact: Train services to Liverpool Cntrl Northern are returning to normal but some services may still be cancelled or delayed. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-31 11:07:03 | Cancellations to services to Liverpool Cntrl Northern | |
Date / Time Resolved | 2024-12-31 11:35:02 | ||
Due to a train fault at Bootle Oriel Road disruption is expected until 12:00 31/12. Impact: Train services to Liverpool Cntrl Northern may be cancelled or delayed. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 23:10:24 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2024-12-30 00:55:01 | ||
Due to signalling problems at Hunts Cross the Hunts Cross line is disrupted. Disruption is expected until the end of the day. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool Cntrl Northern. Customer Advice: Replacement road transport services are conveying passengers between Moorfields and Hunts Cross in both directions until further notice. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 23:10:24 | Trains now running normally to Ormskirk | |
Date / Time Resolved | 2024-12-30 00:55:01 | ||
Due to signalling problems at Hunts Cross the Hunts Cross line is disrupted. Impact: Train services to Ormskirk are now running normally. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 20:35:50 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2024-12-29 23:15:02 | ||
Due to signalling problems at Hunts Cross the Hunts Cross line is disrupted. Disruption is expected until the end of the day. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool Cntrl Northern. Customer Advice: Replacement road transport services are conveying passengers between Moorfields and Hunts Cross in both directions until further notice. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 20:35:50 | Trains now running normally to Ormskirk | |
Date / Time Resolved | 2024-12-29 23:15:02 | ||
Due to signalling problems at Hunts Cross the Hunts Cross line is disrupted. Impact: Train services to Ormskirk are now running normally. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 18:11:38 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2024-12-29 20:40:02 | ||
Due to signalling problems at Hunts Cross the Hunts Cross line is disrupted. Disruption is expected until 22:00 29/12. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool Cntrl Northern. Customer Advice: Replacement road transport services are conveying passengers between Moorfields and Hunts Cross in both directions until further notice. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 18:11:38 | Trains now running normally to Ormskirk | |
Date / Time Resolved | 2024-12-29 20:40:02 | ||
Due to signalling problems at Hunts Cross the Hunts Cross line is disrupted. Impact: Train services to Ormskirk are now running normally. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 15:46:36 | Trains now running normally to Ormskirk | |
Date / Time Resolved | 2024-12-29 18:15:02 | ||
Due to signalling problems at Hunts Cross the Hunts Cross line is disrupted. Impact: Train services to Ormskirk are now running normally. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 15:46:36 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2024-12-29 18:15:02 | ||
Due to signalling problems at Hunts Cross the Hunts Cross line is disrupted. Disruption is expected until 22:00 29/12. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool Cntrl Northern. Customer Advice: Replacement road transport services are conveying passengers between Moorfields and Hunts Cross in both directions until further notice. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 13:25:46 | Trains now running normally to Ormskirk | |
Date / Time Resolved | 2024-12-29 15:55:02 | ||
Due to signalling problems at Hunts Cross the Hunts Cross line is disrupted. Impact: Train services to Ormskirk are now running normally. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 13:25:46 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2024-12-29 15:55:02 | ||
Due to signalling problems at Hunts Cross the Hunts Cross line is disrupted. Disruption is expected until 17:00 29/12. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool Cntrl Northern. Customer Advice: Replacement road transport services are conveying passengers between Moorfields and Hunts Cross in both directions until further notice. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 12:54:04 | Trains now running normally to Ormskirk | |
Date / Time Resolved | 2024-12-29 13:30:03 | ||
Due to signalling problems at Hunts Cross the Hunts Cross line is disrupted. Impact: Train services to Ormskirk are now running normally. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 12:54:04 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2024-12-29 13:30:03 | ||
Due to signalling problems at Hunts Cross the Hunts Cross line is disrupted. Disruption is expected until 15:00 29/12. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool Cntrl Northern. Customer Advice: Replacement road transport services are conveying passengers between Moorfields and Hunts Cross in both directions until further notice. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 12:16:51 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2024-12-29 13:00:02 | ||
Due to signalling problems at Hunts Cross the Hunts Cross line is disrupted. Disruption is expected until 13:00 29/12. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool Cntrl Northern. Customer Advice: Replacement road transport services are conveying passengers between Moorfields and Hunts Cross in both directions until further notice. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 12:16:51 | Trains now running normally to Ormskirk | |
Date / Time Resolved | 2024-12-29 13:00:02 | ||
Due to signalling problems at Hunts Cross the Hunts Cross line is disrupted. Impact: Train services to Ormskirk are now running normally. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 11:44:34 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2024-12-29 12:25:02 | ||
Due to signalling problems at Hunts Cross the Ormskirk and Hunts Cross line is disrupted. Disruption is expected until 13:00 29/12. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool Cntrl Northern. Customer Advice: Replacement road transport services are conveying passengers between Moorfields and Hunts Cross in both directions until further notice. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 11:44:34 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2024-12-29 12:25:02 | ||
Due to signalling problems at Hunts Cross the Ormskirk and Hunts Cross line is disrupted. Disruption is expected until 13:00 29/12. Impact: Train services to Ormskirk may be cancelled. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 10:30:17 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2024-12-29 11:50:01 | ||
Due to signalling problems at Hunts Cross the Ormskirk and Hunts Cross line is disrupted. Disruption is expected until 12:00 29/12. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool Cntrl Northern. Customer Advice: Replacement road transport services are conveying passengers between Moorfields and Hunts Cross in both directions until further notice. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 10:30:17 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2024-12-29 11:50:01 | ||
Due to signalling problems at Hunts Cross the Ormskirk and Hunts Cross line is disrupted. Disruption is expected until 12:00 29/12. Impact: Train services to Ormskirk may be cancelled. |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 10:24:19 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2024-12-29 10:35:02 | ||
Due to signalling problems at Hunts Cross the Ormskirk and Hunts Cross line is disrupted. Disruption is expected until 12:00 29/12. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool Cntrl Northern. Additional Information: Buses have been requested to run between Moorfields and Hunts Cross in both directions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 10:24:19 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2024-12-29 10:35:02 | ||
Due to signalling problems at Hunts Cross the Ormskirk and Hunts Cross line is disrupted. Disruption is expected until 12:00 29/12. Impact: Train services to Ormskirk may be cancelled. Additional Information: Buses have been requested to run between Moorfields and Hunts Cross in both directions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 10:08:25 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2024-12-29 10:30:02 | ||
Due to signalling problems at Hunts Cross the Ormskirk and Hunts Cross line is disrupted. Disruption is expected until 12:00 29/12. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool Cntrl Northern. Additional Information: Buses have been requested to run between Moorfields and Hunts Cross in both directions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 10:08:25 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2024-12-29 10:30:02 | ||
Due to signalling problems at Hunts Cross the Ormskirk and Hunts Cross line is disrupted. Disruption is expected until 12:00 29/12. Impact: Train services to Ormskirk may be cancelled. Additional Information: Buses have been requested to run between Moorfields and Hunts Cross in both directions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 09:53:53 | Alterations to services to Hunts Cross | |
Date / Time Resolved | 2024-12-29 10:10:01 | ||
Due to signalling problems at Hunts Cross the Ormskirk and Hunts Cross line is disrupted. Disruption is expected until 11:15 29/12. Impact: Train services to Hunts Cross will be terminated at and started back from Liverpool Cntrl Northern. Additional Information: Buses have been requested to run between Moorfields and Hunts Cross in both directions |
Route | Hunts Cross | Line | Northern |
---|---|---|---|
Date / Time Reported | 2024-12-29 09:53:53 | Cancellations to services to Ormskirk | |
Date / Time Resolved | 2024-12-29 10:10:01 | ||
Due to signalling problems at Hunts Cross the Ormskirk and Hunts Cross line is disrupted. Disruption is expected until 11:15 29/12. Impact: Train services to Ormskirk may be cancelled. Additional Information: Buses have been requested to run between Moorfields and Hunts Cross in both directions |